Work Profile Report [53W1686]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 30.10.2023
TS Amount (lakhs) : 215.51 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
256.11
Resanction Cost :
256.11
Tentative Cost :
256.11
Exp. Upto Last Fy :
175.58
For CFY 2025-2026
Remaining :
80.53
Demand :
80.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
175.58
Construction Started
Sanction on : 1 year 5 months ago
30 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 3 months 2 weeks from now
13 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग पर जी1 जी2 एवं जी3 का कार्य पूर्ण। पी0सी0 का कार्य प्रगति पर है। -- as on 06-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: