Work Profile Report [53W1551]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1173/।।।(3)/2021-40(सी.आार.आई.एफ.)/2021 दिनांक 27.10.2021
TS Amount (lakhs) : 7753 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7753.00
Resanction Cost :
7914.71
Tentative Cost :
7914.71
Exp. Upto Last Fy :
7,907.09
For CFY 2025-2026
Remaining :
7.62
Demand :
7.60
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7,907.09
Construction Started
Sanction on : 3 years 5 months ago
27 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
99 %
Up to Date :
99 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग निर्माण का कार्य माह 03/2025 में पूर्ण। विविध कार्य प्रगति पर है। -- as on 06-Apr-2025