Work Profile Report [52W560]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-ई-पत्रावली संख्या-35334 लोक निर्माण अनुभाग-2, देहरादून दिनांक 11.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.26
Resanction Cost :
161.26
Tentative Cost :
161.26
Exp. Upto Last Fy :
5.52
For CFY 2025-2026
Remaining :
155.74
Demand :
155.74
Allotment :
45.24
Exp in CFY :
14.56
Total Up to Date Exp :
20.09
Construction Started
Sanction on : 1 year 2 months ago
11 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
10 %
Tentative Completion date on : 2 weeks 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand