Work Profile Report [52W546]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0-212/।।।(2)/2024-01(प्रा0आ0)/2023 दिनांक 31 जनवरी 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
234.02
Resanction Cost :
234.02
Tentative Cost :
234.02
Exp. Upto Last Fy :
227.15
For CFY 2025-2026
Remaining :
6.87
Demand :
6.87
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
227.15
Work completed
Sanction on : 1 year 2 months ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 12/2024 में कार्य पूर्ण। -- as on 14-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand