Work Profile Report [52W509]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी देहरादून के पत्र सं0-691/जि0यो0-01/2023-24 दिनांक 02.06.2023
TS Amount (lakhs) : 8 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
6.09
For CFY 2025-2026
Remaining :
1.91
Demand :
0.40
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.09
Construction Started
Sanction on : 1 year 10 months ago
02 Jun 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 05-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: