Work Profile Report [52W38]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006
TS Amount (lakhs) : 56.7 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.70
Resanction Cost :
56.70
Tentative Cost :
56.70
Exp. Upto Last Fy :
55.64
For CFY 2025-2026
Remaining :
1.06
Demand :
1.06
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
55.64
Work completed
Sanction on : 18 years 6 months ago
25 Sep 2006
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 years 3 weeks ago
31 Mar 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 06/2019 में कार्य पूर्ण। -- as on 19-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand