Work Profile Report [52W26]

सारनी सम्पर्क मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005

TS Amount (lakhs) : 90.53 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

41.70

Resanction Cost :

90.53

Tentative Cost :

90.53

Exp. Upto Last Fy :

88.80

For CFY 2025-2026

Remaining :

1.73

Demand :

1.73

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

88.80

Work completed

Sanction on : 19 years 5 months ago

10 Nov 2005

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 10 months ago

31 May 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
3.000
0
0.000
0.000

Remark

view all

पहाड़ कटान का कार्य 3.00 कि0मी0 माह 05/2023 को पूर्ण, प्रतिकर पत्रावली गठित कर अनुुमोदन पश्चात प्रतिकर वितरण कर दिया जायेगा। -- as on 08-Oct-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: