Work Profile Report [51W1259]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 47588 Dt. 31.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
156.73
Resanction Cost :
156.73
Tentative Cost :
156.73
Exp. Upto Last Fy :
151.70
For CFY 2025-2026
Remaining :
5.03
Demand :
5.03
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
151.70
Work completed
Sanction on : 1 year 2 months ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week ago
13 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: