Work Profile Report [51W1214]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E Letter No 49205 Dt. 10.10.2023
TS Amount (lakhs) : 312.46 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
312.46
Resanction Cost :
312.46
Tentative Cost :
312.46
Exp. Upto Last Fy :
296.16
For CFY 2025-2026
Remaining :
16.30
Demand :
16.30
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
296.16
Work completed
Sanction on : 1 year 6 months ago
10 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 6 days ago
28 Mar 2025
Actual Completion Date : 4 weeks 2 days ago
25 Mar 2025
Physical Linear Components
Remark
कार्य नाबार्ड मे स्वीकृत होने से पूर्व उक्त कार्य मे 92.04 लाख का व्यय राज्य योजना से किया जा चुका है ।कार्य पूर्ण। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: