Work Profile Report [4W568]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 266/(1)111(2)/20-41(प्रा.आ.)/2006 दिनांक 10.01.2020
TS Amount (lakhs) : 664.72 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
664.72
Resanction Cost :
664.72
Tentative Cost :
575.64
Saving
89.08
Exp. Upto Last Fy :
560.19
For CFY 2025-2026
Remaining :
104.53
Demand :
6.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
560.19
In Maintenance After Completion
Sanction on : 5 years 3 months ago
10 Jan 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 5 months ago
02 Nov 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। कार्य 3 वर्षीय अनुरक्षण के अन्तर्गत है। -- as on 21-Mar-2025
Assets :