Work Profile Report [4W130]

fभfकयासैन के अन्तर्गत नौला-स्योैतरा-महरनैल मोटर मार्ग का एस.सी.पी. के अन्तर्गत नव fनर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं 830 /111(2)/08 -29 (पा्र.आ.) दि..24.3.08

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

233.00

Resanction Cost :

233.00

Tentative Cost :

233.00

Exp. Upto Last Fy :

2.68

For CFY 2025-2026

Remaining :

230.32

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

2.68

Work deferred

Sanction on : 17 years 1 month ago

24 Mar 2008

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

पी.एम.जी.एस.वाई. खण्ड द्वाराहाट के अन्तर्गत नौला से थिरोली मोटर मार्ग स्वीकृत है, जिसका समरेखन नौला से स्यौतरा (किमी. 5.75) तक समान है इस सम्बन्ध में अधिशासी अभियन्ता, पी.एम.जी.एस.वाई. खण्ड द्वाराहाट से वार्ता की गयी । पी.एम.जी.एस.वाई. सड़क निर्माण का कार्य पूर्ण। शेष आगे की लम्बाई में सर्वेक्षण का कार्य प्रगति पर है। समरेखन विवाद -- as on 04-Sep-2023

Rating : 1

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: