Work Profile Report [4W103]

fवनायक-fरखाड़ी- कोfटयाग मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं. 2491 /111-2/06 -36(प्रा्र.आ.)/06 दिनांक 19.9.06

TS Amount (lakhs) : 124.6 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

124.60

Resanction Cost :

124.60

Tentative Cost :

112.63

Saving

11.97

Exp. Upto Last Fy :

106.63

For CFY 2025-2026

Remaining :

17.97

Demand :

1.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

106.63

Work completed

Sanction on : 19 years 2 months ago

19 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 years 11 months ago

31 Dec 2020

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
4
4.000
0
0.000
0.000

Remark

view all

Overall Saving 11.97 has been recorded as expected cost of work reduced from 124.6 to 112.63 . -- as on 18-Dec-2025

Rating : 100

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: