Administrative Approval Detail : E-File-39499 Dt- 02-08-2023
TS Amount (lakhs) : 128.73 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
128.73
Resanction Cost :
128.73
Tentative Cost :
128.73
Exp. Upto Last Fy :
25.72
For CFY 2025-2026
Remaining :
103.01
Demand :
50.00
Allotment :
27.00
Exp in CFY :
10.62
Total Up to Date Exp :
36.34
Construction Started
Sanction on : 1 year 10 months ago
02 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
75 %
Tentative Completion date on : 6 months 3 weeks from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 04-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: