Work Profile Report [47W577]
Tenders
alerts
Documents
Samples
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 146 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
146.00
Resanction Cost :
146.00
Tentative Cost :
146.00
Exp. Upto Last Fy :
142.12
For CFY 2025-2026
Remaining :
3.88
Demand :
3.89
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
142.12
Work completed
Sanction on : 1 year 8 months ago
31 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
26 Feb 2024
Actual Completion Date : 1 year 1 month ago
26 Feb 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष । -- as on 24-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: