Work Profile Report [47W541]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल सं0-36456 दिनंाक 27.02.2023
TS Amount (lakhs) : 133.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
133.22
Resanction Cost :
133.22
Tentative Cost :
133.22
Exp. Upto Last Fy :
94.74
For CFY 2025-2026
Remaining :
38.48
Demand :
38.48
Allotment :
38.48
Exp in CFY :
17.07
Total Up to Date Exp :
111.81
Work completed
Sanction on : 2 years 3 months ago
27 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
100 %
Tentative Completion date on : 2 weeks 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 04-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: