Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.80
Resanction Cost :
43.80
Tentative Cost :
43.80
Exp. Upto Last Fy :
38.36
For CFY 2025-2026
Remaining :
5.44
Demand :
5.44
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
38.36
Alignment Approved
Sanction on : 11 years 4 months ago
29 Jan 2014
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 1 month 3 weeks from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुपालन आख्या नोड़ल अधिकारी द्वारा दिनांक 09.12.2024 को आॅन लाईन सत्यापित की जा चुकी है। 0 -- as on 04-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: