Work Profile Report [46W333]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 2719/।।। (2)/17-25 (प्रा0आ0)/2017 टी0सी0 दिनांक 09 अक्टूबर 2017
TS Amount (lakhs) : 74.33 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
126.38
Resanction Cost :
126.38
Tentative Cost :
126.38
Exp. Upto Last Fy :
28.10
For CFY 2025-2026
Remaining :
98.28
Demand :
98.28
Allotment :
78.02
Exp in CFY :
42.32
Total Up to Date Exp :
70.41
Construction Started
Sanction on : 7 years 8 months ago
09 Oct 2017
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 3 months 3 weeks ago
15 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पार्ट-2 के कार्य प्रगति पर है। -- as on 21-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: