Work Profile Report [45W144]

माननीय मुख्यमंत्री जी की घोषणा संख्या-712/2015 के अन्तर्गत सौंप-आर्स मोटर मार्ग का नव निर्माण (या0सं0-290/2007)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0-2700(1)/।।।(2)/11-38(प्रा0आ0)/2011, दि0 18.07.2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

37.80

Resanction Cost :

37.80

Tentative Cost :

37.80

Exp. Upto Last Fy :

35.21

For CFY 2025-2026

Remaining :

2.59

Demand :

2.59

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

35.21

Work completed

Sanction on : 13 years 9 months ago

18 Jul 2011

Physical Progress:

At start of FY 2025-2026 :

95 %

Up to Date :

95 %

Tentative Completion date on : 1 month 6 days from now

31 May 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
3.000
0
0.000
0.000

Remark

view all

मोटर मार्ग निर्माण कार्य पूर्ण। प्रथम चरण की स्वीकृति के सापेक्ष मुआवजा वितरण की कार्यवाही पूर्ण । एक काश्तकार द्वारा अपनी क्षतिग्रस्त खेत में मलवा सफाई कर दीवार लगाने की मांग की जा रही है तथा क्षतिग्रस्त पैदल मार्ग का पुनर्निर्माण किया जाना है। -- as on 11-Apr-2025

Rating : 96

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: