Work Profile Report [44W701]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0- 3930/111(2)/09-08(एम0एल0ए0)/08 टी0सी0 दिनांक 02.03.2009
TS Amount (lakhs) : 105 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy :
102.15
For CFY 2025-2026
Remaining :
2.85
Demand :
2.85
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
102.15
Construction Started
Sanction on : 16 years 1 month ago
02 Mar 2009
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 1 month 5 days from now
30 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.50 कि0मी0 ल0 में पहाड कटान का कार्य पूर्ण। शेष लं0 में कार्य प्रगति पर। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: