Work Profile Report [44W622]
Tenders
Project Activities
alerts
Administrative Approval Detail : शासनादेश संख्या-4990(1)/।।।(2)/21-39 (प्रा0आ0)/2018 दिनंाक 22 अक्टूबर, 2021
TS Amount (lakhs) : 6287.93 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6886.20
Resanction Cost :
6886.20
Tentative Cost :
6886.20
Exp. Upto Last Fy :
5,886.07
For CFY 2025-2026
Remaining :
1,000.13
Demand :
1,000.13
Allotment :
418.13
Exp in CFY :
354.29
Total Up to Date Exp :
6,240.36
Construction Started
Sanction on : 4 years 1 month ago
22 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
72 %
Up to Date :
93 %
Tentative Completion date on : 2 weeks 1 day from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Mastic work Second Layer 100% completed.
2- Hut portion right/Left site 100% completed.
3- Installation of Link & wind Shoes 100%
4- Painting on Deck 98% completed.
5- Glass panels supply 396 No.
6- Installation of Glass Panels on deck 396 No.
7- Railing 100% Completed.
-- as on 17-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: Laxman jhula Pedestrain Bridge