Work Profile Report [43W558]

भागीरथीपुरम खेमडा कुण्डाली मो0 मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 89/लो0नि0-01/04 प्रा0आ0/04 दि0 06.02.2004 एवं शा0 सं0 15मेमो /111(2)/20 /07 प्रा0आ0/2019 दि0 13.03.2020

TS Amount (lakhs) : 346.16 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

69.50

Resanction Cost :

346.16

Tentative Cost :

346.16

Exp. Upto Last Fy :

289.81

For CFY 2025-2026

Remaining :

56.35

Demand :

56.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

289.81

Construction Started

Sanction on : 21 years 2 months ago

06 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

80 %

Up to Date :

80 %

Tentative Completion date on : 3 months 6 days from now

31 Jul 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5.5
5.500
0
0.000
0.000

Remark

view all

चै0 5/20 तक पहाड कटान कार्य पूर्ण । किमी0 4 तक पार्ट द्वितीय कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 23-Apr-2025

Rating : 86

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: