Administrative Approval Detail : जिलाधिकारी का पत्र संख्या 14/जि0यो0-03/(अर्थ एवं संख्या) /2024-25 दिनांक 20.07.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy :
2.50
For CFY 2025-2026
Remaining :
2.50
Demand :
2.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.50
Work completed
Sanction on : 9 months 4 days ago
20 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 04-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: