Work Profile Report [40W492]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा॰सं॰ 28022-0465/2023 दिनंाक 28.03.202
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.29
Resanction Cost :
79.29
Tentative Cost :
79.29
Exp. Upto Last Fy :
63.67
For CFY 2025-2026
Remaining :
15.62
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
63.67
Work completed
Sanction on : 2 years 3 weeks ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 month 6 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 04-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: