Work Profile Report [40W12]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 63(1)/।।।-2/06/91(प्रा॰आ॰)/05 दि0 16.01.06 एवं शा॰सं॰ 1679/।।।(2)/18-91 (प्रा॰आ॰)/2005 दिनांक 26-04-2018
TS Amount (lakhs) : 84 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.00
Resanction Cost :
223.34
Tentative Cost :
223.34
Exp. Upto Last Fy :
209.04
For CFY 2025-2026
Remaining :
14.30
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
209.04
Work completed
Sanction on : 19 years 3 months ago
16 Jan 2006
Physical Progress:
At start of FY 2025-2026 :
97 %
Up to Date :
97 %
Tentative Completion date on : 3 years 3 weeks ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। काश्तकारों को मुआवजा वितरण किया जाना है। -- as on 21-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand