Work Profile Report [3W83]

शशिखाल तराड़ जाख मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा.सं. 299लो.नि.-2/2004-16(प्रा.आ.)/04 दि. 28.02.04

TS Amount (lakhs) : 173.25 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

347.50

Resanction Cost :

347.50

Tentative Cost :

347.50

Exp. Upto Last Fy :

93.64

For CFY 2025-2026

Remaining :

253.86

Demand :

150.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

93.64

none

Sanction on : 21 years 9 months ago

28 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

52 %

Tentative Completion date on : 8 months 2 weeks ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
25
11.7
2.240
9.46
1.700
0.000

Remark

view all

1.70 किमी. लम्बाई की नाप भूमि मंे अनुबन्ध गठित कर पहाड़ कटान का कार्य प्रगति मंे है। -- as on 28-Nov-2025

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: