Work Profile Report [3W7]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 2751/111-2/06-49(प्रा0आ0)/06 दि. 22.11.06
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
469.72
Resanction Cost :
469.72
Tentative Cost :
356.14
Saving
113.58
Exp. Upto Last Fy :
248.04
For CFY 2025-2026
Remaining :
221.68
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
248.04
Construction Started
Sanction on : 18 years 5 months ago
22 Nov 2006
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान एवं 5.00 किमी. लम्बाई में पार्ट-।। का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: