Administrative Approval Detail : शा0सं0 498(1)/।।।(2)/22-08(एमएलए)/2017 टीसी दिनांक 07.01.2022
TS Amount (lakhs) : 28.27 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
28.27
Resanction Cost :
28.27
Tentative Cost :
28.27
Exp. Upto Last Fy :
0.15
For CFY 2025-2026
Remaining :
28.12
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.15
Construction Started
Sanction on : 3 years 3 months ago
07 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.20 किमी0 में पहाड कटान के उपरान्त ग्रमीणों द्वारा विवाद किया गया। -- as on 27-Mar-2025