Work Profile Report [39W63]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 764/।।।(2)/08-85 (प्रा0आ0)/07 दि. 24.03.08
TS Amount (lakhs) : 107.7 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
110.25
Resanction Cost :
110.25
Tentative Cost :
110.25
Exp. Upto Last Fy :
102.30
For CFY 2025-2026
Remaining :
7.95
Demand :
7.93
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
102.30
Construction Started
Sanction on : 17 years 1 month ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 किमी0 में पहाड कटान कार्य पूर्ण। दायित्व शेष। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: