Work Profile Report [39W470]

ग्राम निरवाली-धारकोट में अलकनन्दा नदी पर 85 मीटर विस्तार झूला पुल का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 935/18-(2)/15-12(11)/2014टी.सी. दिनांक 30.03.2015

TS Amount (lakhs) : 377.51 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

377.51

Resanction Cost :

377.51

Tentative Cost :

377.51

Exp. Upto Last Fy :

197.76

For CFY 2025-2026

Remaining :

179.75

Demand :

100.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

197.76

Construction Started

Sanction on : 10 years 3 weeks ago

30 Mar 2015

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

50 %

Tentative Completion date on : 3 months 3 weeks ago

31 Dec 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (85m)
1 (85m)
0 (0.000m)
1 (85m)
0 (0.000m)
0 (0.000m)

Remark

view all

उत्तराखण्ड शासन के पत्र संख्या 506/एक्स-4-15/1(25)/2015 दिनांक 06.01.2016 द्वारा विधिवत स्वीकृति प्राप्त।
बांये एंकर कम टावर का 90 प्रतिशत कार्य पूर्ण (राफ्ट, फाउण्डेशन व सुरक्षात्मक कार्य)। दायें एबटमेन्ट का कार्य 100 प्रतिशत पूर्ण। सेतु का फैब्रिकेशन का कार्य वर्कशाॅप में प्रगति में। दांयी ओर एंकर ब्लाॅक की खुदाई का कार्य प्रगति पर है।
-- as on 27-Mar-2025

Rating : 52

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: