Administrative Approval Detail : शा.सं. 1/216291/2024 ई फाइल संख्या 54684 लोक निर्माण अनुभाग 02 दिनांक 06.06.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.09
Resanction Cost :
124.09
Tentative Cost :
124.09
Exp. Upto Last Fy :
60.64
For CFY 2025-2026
Remaining :
63.45
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
60.64
Work completed
Sanction on : 10 months 2 weeks ago
06 Jun 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 weeks 1 day ago
26 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.20 किमी0 में दीवार निर्माण एवं 14 नं0 स्कपर का निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 02-Apr-2025