Work Profile Report [36W57]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 3181/111(2)/ 06-52(प्रा.आ.)/06 टी.सी.-1 दि. 14.12.06
TS Amount (lakhs) : 33.6 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
33.60
Resanction Cost :
33.60
Tentative Cost :
33.60
Exp. Upto Last Fy :
0.28
For CFY 2025-2026
Remaining :
33.32
Demand :
33.32
Allotment :
33.32
Exp in CFY :
1.47
Total Up to Date Exp :
1.75
Construction Started
Sanction on : 18 years 8 months ago
14 Dec 2006
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
10 %
Tentative Completion date on : 1 month 2 weeks from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
फिलिंग एवं दिवार निर्माण का कार्य प्रगति में। -- as on 02-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: