Work Profile Report [31W125]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : -शा0सं0-5384 1/(।।।) 2/10-02 एम0एल0ए0/2010 दि0- 13/12/2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy :
6.72
For CFY 2025-2026
Remaining :
5.88
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.72
Alignment Approved
Sanction on : 14 years 4 months ago
13 Dec 2010
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 3 months 3 weeks ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के अन्तर्गत प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: