Work Profile Report [30W253]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5384/।।।:2ः/10-02:एम0एल0ए0ः/10 दि0 13-12-10
TS Amount (lakhs) : 18.64 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy :
30.83
For CFY 2025-2026
Remaining :
6.97
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
30.83
Work completed
Sanction on : 14 years 7 months ago
13 Dec 2010
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निर्माण कार्य पूर्ण हो चुका है। -- as on 08-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: