Work Profile Report [2W586]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No.50429 date 18.05.2023
TS Amount (lakhs) : 257.45 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
257.45
Resanction Cost :
257.45
Tentative Cost :
257.45
Exp. Upto Last Fy :
221.44
For CFY 2025-2026
Remaining :
36.01
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
221.44
Construction Started
Sanction on : 1 year 11 months ago
18 May 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 3 months 5 days from now
30 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डामरीकरण का कार्य पूर्ण।शेष कार्य प्रगति पर। ठेकेदार को पेनाल्टी लगाने का नोटिस दिया गया । -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: