Work Profile Report [2W25]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2120/।।।(2)/16-08(प्रा.आ.)/2004टी.सी. दि0 11-07-2016
TS Amount (lakhs) : 155.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
155.98
Resanction Cost :
155.98
Tentative Cost :
93.80
Saving
62.18
Exp. Upto Last Fy :
85.80
For CFY 2025-2026
Remaining :
70.18
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
85.80
Construction Started
Sanction on : 9 years 5 months ago
11 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
78 %
Up to Date :
78 %
Tentative Completion date on : 1 year 3 months ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 62.18 has been recorded as expected cost of work reduced from 155.98 to 93.80 . -- as on 16-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: