Work Profile Report [23W1244]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/249188/2024, e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.01
Resanction Cost :
48.01
Tentative Cost :
48.01
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
48.01
Demand :
47.91
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 6 months 1 day ago
23 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 15-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand