Administrative Approval Detail : G.O. no.- I/176048/2023 e-file no.- 62543
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.53
Resanction Cost :
47.53
Tentative Cost :
36.00
Saving
11.53
Exp. Upto Last Fy :
37.25
For CFY 2025-2026
Remaining :
10.28
Demand :
3.92
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
37.25
Work completed
Sanction on : 1 year 4 months ago
18 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 months 1 week ago
12 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Apr-2025