Work Profile Report [23W1211]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/176048/2023 e-file no.- 62543
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.19
Resanction Cost :
18.19
Tentative Cost :
18.00
Saving
0.19
Exp. Upto Last Fy :
13.66
For CFY 2025-2026
Remaining :
4.53
Demand :
2.06
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
13.66
Work completed
Sanction on : 1 year 4 months ago
18 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
06 Aug 2024
Actual Completion Date : 9 months 3 weeks ago
02 Jul 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: