Work Profile Report [22W1492]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-file No 70174/61
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.42
Resanction Cost :
41.42
Tentative Cost :
41.42
Exp. Upto Last Fy :
1.99
For CFY 2025-2026
Remaining :
39.43
Demand :
30.00
Allotment :
39.43
Exp in CFY :
34.40
Total Up to Date Exp :
36.39
Construction Started
Sanction on : 11 months 3 weeks ago
19 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाॅप कोट तक कार्य पूर्ण। पी0सी0 का कार्य अवशेष। -- as on 30-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: