Work Profile Report [22W1476]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file No 58555/60
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
57.80
Resanction Cost :
57.80
Tentative Cost :
57.80
Exp. Upto Last Fy :
42.15
For CFY 2025-2026
Remaining :
15.65
Demand :
12.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
42.15
Construction Started
Sanction on : 1 year 1 month ago
01 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 4 months 3 weeks ago
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 20-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: