Work Profile Report [22W1435]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT E-File No.51385 , dt. 27.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.02
Resanction Cost :
54.02
Tentative Cost :
54.02
Exp. Upto Last Fy :
26.61
For CFY 2025-2026
Remaining :
27.41
Demand :
0.00
Allotment :
2.33
Exp in CFY :
2.33
Total Up to Date Exp :
28.94
Work completed
Sanction on : 1 year 7 months ago
27 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
26 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: