Work Profile Report [22W1426]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/46/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 12-10-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.36
Resanction Cost :
46.36
Tentative Cost :
46.36
Exp. Upto Last Fy :
29.86
For CFY 2025-2026
Remaining :
16.50
Demand :
16.00
Allotment :
4.42
Exp in CFY :
4.42
Total Up to Date Exp :
34.27
Work completed
Sanction on : 1 year 7 months ago
12 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
100 %
Tentative Completion date on : 7 months 4 weeks ago
11 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 20-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand