Work Profile Report [22W1369]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 25/54 budget road safety (23-24)
TS Amount (lakhs) : 96.82 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
96.82
Resanction Cost :
96.82
Tentative Cost :
96.82
Exp. Upto Last Fy :
88.53
For CFY 2025-2026
Remaining :
8.29
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
88.53
Work completed
Sanction on : 2 years 2 days ago
20 Jun 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 5 months ago
13 Jan 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 13-Jul-2024