Work Profile Report [22W1333]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन का पत्रांक 20/4 (2), दिनाॅक 06.01.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
329.02
Resanction Cost :
230.31
Tentative Cost :
230.31
Exp. Upto Last Fy :
228.24
For CFY 2025-2026
Remaining :
2.07
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
228.24
Work completed
Sanction on : 3 years 11 months ago
06 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 0.06 has been counted as tentative cost increased from 230.25 to 230.31 . -- as on 28-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: