Work Profile Report [20W9]

हलियाडोब लछीमा दशौली ओखरानी नाचनी मोटर मार्ग का विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 774/111 (2)/06 -13 (प्रा0आ0) /06 दि0 28/3/06

TS Amount (lakhs) : 178 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

178.00

Resanction Cost :

178.00

Tentative Cost :

54.72

Saving

123.28

Exp. Upto Last Fy :

42.73

For CFY 2025-2026

Remaining :

135.27

Demand :

11.00

Allotment :

10.69

Exp in CFY :

10.69

Total Up to Date Exp :

53.42

Work deferred

Sanction on : 19 years 8 months ago

28 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

30 %

Tentative Completion date on : 2 years 11 months from now

15 Dec 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

Overall Saving 123.28 has been recorded as expected cost of work reduced from 178 to 54.72 . -- as on 15-Dec-2025

Rating : 27

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: