Work Profile Report [20W533]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E file N0- 55281/XXXVI(2)/23/8-budget/2023 dt- 06.06.2023
TS Amount (lakhs) : 443.88 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
477.50
Resanction Cost :
477.50
Tentative Cost :
477.50
Exp. Upto Last Fy :
77.31
For CFY 2025-2026
Remaining :
400.19
Demand :
345.00
Allotment :
104.94
Exp in CFY :
104.94
Total Up to Date Exp :
182.25
Construction Started
Sanction on : 2 years 6 months ago
29 May 2023
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
40 %
Tentative Completion date on : 10 months 4 weeks from now
14 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
भवन में आतंरिक प्लास्टर का कार्य पूर्णl प्रथम तल में floor टाइल्स फिक्सिंग का कार्य गतिमान l -- as on 04-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand