Work Profile Report [1W70]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65 (प्रा0आ0) / 07 दिनंाक 24.03.2008
TS Amount (lakhs) : 105 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy :
23.88
For CFY 2025-2026
Remaining :
81.12
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
23.88
Work completed
Sanction on : 17 years 1 month ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work Complete -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand