Work Profile Report [18W879]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन सं0 7349/।।।(2)/2024-01 (प्रा0आ0़)/2023 ई- 56385 लोक निर्माण अनुभाग-2 दिनांक 06-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
470.18
Resanction Cost :
470.18
Tentative Cost :
470.18
Exp. Upto Last Fy :
388.13
For CFY 2025-2026
Remaining :
82.05
Demand :
82.05
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
388.13
Construction Started
Sanction on : 5 months 2 weeks ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
50 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
9000 मी0 लम्बाई मे क्रैश बैरियर का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 31-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: