Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या-77451, लोक निर्माण अनुभाग-2 देहरादून दिनांक 30 सितम्बर 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
229.31
Resanction Cost :
229.31
Tentative Cost :
229.31
Exp. Upto Last Fy :
12.04
For CFY 2025-2026
Remaining :
217.27
Demand :
150.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
12.04
Construction Started
Sanction on : 6 months 3 weeks ago
30 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 8 months 6 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबंध गठित। सोलिंग का कार्य प्रगति पर है। -- as on 15-Feb-2025