Work Profile Report [17W406]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E- File No. 69724 Lok Nirman Anubhag-2 date 14-03-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.90
Resanction Cost :
4.90
Tentative Cost :
4.90
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
4.90
Demand :
4.90
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 1 year 1 month ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 10-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand